Rillieux-la-Pape (69)
Main building with 2,900 m² of usable floor area / 4,100 m² total floor area: 1 25-meter sports pool, 8 lanes with bleachers, 1 190-m² leisure pool, 1 225-m² pool for swimming lessons and aquatic activities, 1 75-m² paddling pool, 1 wellness area with sauna, steam room and spa.
7,000-m² outdoor park with coping , play area and water slide.
• Project owner: DEMATHIEU BARD IMMOBILIER – SEMOP du Loup Pendu
• Architect: CHABANNE + PARTENAIRES
• Structural design office: CERBETON
• Fluid dynamics/roads and utility works/environmental quality design office: KEO INGENIERIE
• Acoustics design office: GENIE ACOUSTIQUE
• Duration of work : 19 months
• Consumption targets: 3,100 kWhPE/m2 of pool surface/year and 99 L/bather
• Shallow footing foundations
• Reinforced concrete infrastructure
• Metal building frame
• Self-protected waterproofing on pool shell, single- and double-skin metal cladding, concrete coating, aluminum exterior joinery and curtain walls.
• Heating system connected to the heating network, supplementary heating via gas boiler, hot water heating via heating system, underfloor heating for coping, radiators for technical facilities, thermodynamic air treatment in indoor pool areas.
• Usable floor area: 2,900 m²
• Floor space: 4,100 m²
• Outdoor park: 7,000 m²
• Total number of integration hours: 2,700 hours
• Average workforce on site: 30 people