CONSTRUCTION OF A GENERAL EDUCATION HIGH SCHOOL FOR 900 STUDENTS

Construction of a general education high school for 900 students, with 6,036 m² of usable floor area, including a cafeteria, six staff housing units, and a multi-sport gymnasium with 1,534 m² of usable floor area located outside the high school complex in the Châteaurenard sports field.

Project owner : AREA PACA
Project manager : MARCIANO ARCHITECTURE and José MORALES
Methods design office : LOGIK
Structural design office : INGENIERIE 84
Duration of work : 15 months
Energy performance : RT 2012 (French thermal regulation standards)
Labels and certifications : Low Nuisance Worksite / Mediterranean Sustainable Building (BDM Bronze certification)
Prizes and awards : Winning project in the 2020-2021 Technal Aluminium Architecture Awards

CONSTRUCTION METHOD

  • • Buildings laid on shallow foundations
  • • Walls created with cast-in-place concrete
  • • Floors made of precast slabs + compression slab
  • • Precast facade columns
  • • All visible concrete is low carbon
  • • Gymnasium roof support beams in pre-stressed concrete

SPECIFIC TECHNICAL FEATURES

  • • Low-carbon concrete
  • • Gymnasium built with very high walls (11 meters)
  • • Tree trunk-like columns in concrete (courtyard supports)
  • • 29.5 ml prestressed beams
  • • Patterned concrete
  • • Note : the aluminum exterior joinery work package (€1,500,000) was carried out by own production teams

KEY WORKSITE FIGURES

Earthworks : 8,000 m3
Usable floor area : 6,036 m² + 6 staff housing units + a 1,534 m² gym
Formwork : 65,000 m²
Concrete : 10,500 m3
Steel : 600 metric tons
Integration hours : 10,100
Average workforce on site : 50 workers, 3 site managers