Home > Projets > Marie Curie Middle School

Fontoy (57)

DBOM CONTRACT FOR THE CONSTRUCTION, MAINTENANCE AND UPKEEP OF MARIE CURIE MIDDLE SCHOOL IN FONTOY

The work includes the demolition of the existing structure and construction of a new building with 21 classrooms, cafeteria and three staff accommodation units.
The project is broken down into phases, during which the school will remain open.
Modular units were installed in the school courtyard for students.

Project owner: The Moselle Department
Assistant project owner: HQE consultant: ALTEREA
Contracting consortium: DEMATHIEU BARD (lead) – KL ARCHITECTES/BAGARD ET LURON (architects) – OTE/OTELIO (Fluid dynamics and environmental design) – OMNITECH (Structural design office) – DEMATHIEU BARD MAINTENANCE (maintenance)
Duration of work: 25 months (including 8-month design phase) and 36 months of maintenance
Labels and certifications: BBC Effinergie

CONSTRUCTION METHOD

• Concrete post and beam structure
• Facade in timber panels
• Exterior joinery in triple-glazed aluminum, to meet passive building standards

SPECIAL WORKS

  • • 928 m² of timber-frame walls
  • • 1,200 m² of Caraïne metal cladding
  • • 400 m² of Eternit fiber cement sheeting
  • • 120 m² collective kitchen

KEY WORKSITE FIGURES

Demolition: 620 metric tons
Asbestos removal: 3,500 m²
Earthworks: 7,500 m3
Formwork: 2,850 m
Concrete: 2,100 m3
Steel: 70 metric tons
Sealing: 2,200 m²
School capacity: 560 students
Number of integration hours: 4,500 hours
Average number of supervisors and workers: 4 supervisors and 15 workers

Caption: Marie Curie Middle School in Fontoy – © KL ARCHITECTES/BAGARD ET LURON