Lyon (69)
Construction as general contractor of 333 housing units (130-room student residence, 102 private homes, 39 first-time-buyer homes, 62 social housing homes, 253 underground parking spaces).
• Project owner: DEMATHIEU BARD IMMOBILIER / COFFIM
• Architect: MP&A
• Design office - structure: ICS
• Design office – fluids / building economist: TPF
• Duration of works: 24 months
• General contractor, all trades
• Demolition of existing buildings
• Removal and evacuation of materials containing asbestos
• Selective deconstruction, sorting and evacuation of materials
• Special foundations, lowering of groundwater
• Facade system in Thermédia® concrete
• Base in decorative concrete
• Exterior joinery and roller shutters in PVC
• H&E 2012 Profile A
• Qualitel RT2012-10%
• Grand Lyon 2013 guidelines – performance level